Successful Projects -> Norwich Park ROM Upgrade

Norwich Park ROM Upgrade

Primary Contact: Graeme Caddy, Coal Preparation Plant Manager
McBryde's Project Managers: Mark McBryde
4 Supervisors, 48 Tradesman and Assistants
Planned Shutdown Period: 21 Days
Acutal Shutdown Period: 23 Days (including 3 day approved extension)
Referee: David Chatto, Washplant Manager

Removing Apron Feeder Discharge Chute



Crusher Feed Chute Removal

Removing Concrete Plinths



Installing new crusher (58 tonne)

Crusher has landed

Installing Retaining Wall

ROM Bobcat Access Ramp