Norwich Park ROM Upgrade
Primary Contact: Graeme Caddy, Coal Preparation Plant Manager
McBryde's Project Managers: Mark McBryde
4 Supervisors, 48 Tradesman and Assistants
Planned Shutdown Period: 21 Days
Acutal Shutdown Period: 23 Days (including 3 day approved extension)
Referee: David Chatto, Washplant Manager |
Removing Apron Feeder Discharge Chute

Crusher Feed Chute Removal
Removing Concrete Plinths

Installing new crusher (58 tonne)
|
Crusher has landed
Installing Retaining Wall
ROM Bobcat Access Ramp |