McBryde Corporations  
 

Successful Projects -> BMA Thermal Coal Plant Traid Loadout

BMA Thermal Coal Plant Traid Loadout

Primary Contact: David Chatto - Washplant Maintenance Superintendent
BMA Project Manager: Murray Kingman
80 Tradesman and Assistants
Planned Shutdown Period: 10-10-21 Days
Actual Shutdown Period: 8-9-23 Days
Referee: Murray Kingman

3D Model of New Train Loadout Area


Original Conveyor C7 Head End & Loadout Bin


Original Loadout Bin Removal


Feeder Tunnel Section Removed for New Feeder Room


Pre-Cast Wall for New Feeder Room


Roof of New Feeder Room


New Feeder Room


Conveyor C7 Gantry & Trestles




Conveyor C7 Dual Drive Base


New Conveyor C7 & Loadout Bin


Original ROM Bridge


New ROM Bridge